FREE QUOTE CALL (613) 370-0158

Rego construction group
  • Home
  • Our Services
    • Hoisting and Rigging
    • Concrete Solutions
    • Moving and Transportation
    • Demolition Services
  • Contact
  • Projects
    • Chiller rooftop lift
    • Elevator pit Ottawa
    • Cooling tower foundation
    • Mechanical demolition
  • Partner With Us
    • HVAC Contractors
    • Electrical Contractors
    • Plumbing Contractors
  • media
    • Socials
    • Blog
    • Customer Testimonials
  • More
    • Home
    • Our Services
      • Hoisting and Rigging
      • Concrete Solutions
      • Moving and Transportation
      • Demolition Services
    • Contact
    • Projects
      • Chiller rooftop lift
      • Elevator pit Ottawa
      • Cooling tower foundation
      • Mechanical demolition
    • Partner With Us
      • HVAC Contractors
      • Electrical Contractors
      • Plumbing Contractors
    • media
      • Socials
      • Blog
      • Customer Testimonials
Rego construction group
Contact us
  • Home
  • Our Services
    • Hoisting and Rigging
    • Concrete Solutions
    • Moving and Transportation
    • Demolition Services
  • Contact
  • Projects
    • Chiller rooftop lift
    • Elevator pit Ottawa
    • Cooling tower foundation
    • Mechanical demolition
  • Partner With Us
    • HVAC Contractors
    • Electrical Contractors
    • Plumbing Contractors
  • media
    • Socials
    • Blog
    • Customer Testimonials
Contact us

Mechanical Demolition on a Six-Day Deadline, Ottawa

Intro

A full mechanical demolition with a hard six-day deadline: strip every plumbing and HVAC system out of the building without blowing the schedule. Rego finished it in three 12-hour shifts, half the time allowed. 

The Challenge

The scope was a complete mechanical strip-out under an aggressive six-day window: all existing plumbing and HVAC, piping, electrical wiring, 22 ceiling-mounted cooling units, three rooftop condensers, and 12 compressors. On a deadline that tight, coordination and crew output are the whole job. 

How Rego Did It

Through careful coordination and a crew that dedicated itself to the timeline, the work was completed in just three 12-hour shifts, well ahead of the six days allotted. The team kept to strict safety standards throughout and minimized disruption while moving at pace. 

Outcome

The entire demolition was delivered in half the allotted time, safely and cleanly, proof Rego can hold quality under a compressed schedule. 

Project Specs

  • Scope: full mechanical demolition, plumbing and HVAC removal
  • Removed: piping, electrical wiring, 22 ceiling-mounted cooling units, 3 rooftop condensers, 12 compressors
  • Deadline: 6 days
  • Completed in: three 12-hour shifts
  • Location: Ottawa and surrounding areas
  • Service: Demolition


On a tight demolition schedule? Send the scope and site address for a quote. Call or text (613) 370-0158. 

Contact

Photos

    • Home
    • Hoisting and Rigging
    • Concrete Solutions
    • Moving and Transportation
    • Demolition Services
    • Contact

    Rego Construction Group

    4311 Navan Rd, Ottawa, ON K4B 1H9, Canada

    (613) 370-0158

    Copyright © 2026 Rego construction group - All Rights Reserved.


    Powered by

    This website uses cookies.

    We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

    DeclineAccept